Sometimes you may have a task that you wish to split so it's scheduled over a few days or split between two people.
SPLITTING TASKS
To split a task simply click on the task you wish to split and when the pop up appears click Split Task
To split a task you can move the slider to determine how you want to split the task. If you leave the slider where it is it'll split the task time 50:50
Or you can move the slider to determine how you want to split the task. In the example above we've split the task so one task is 3 hours 30 minutes and the other is 6 hours 30 minutes. Once you're done click Split
You have now created two tasks
You can now grab the tasks and move them around the Task Calendar. You could keep them assigned to the same person and just move the tasks horizontally so they're scheduled for different days
Or you can move the tasks vertically so they're assigned to different people. In the example above the task was split in two and is now assigned to Susan Fraser and George Butler.
Another option might be to move one of the Tasks back into the Unassigned Tasks section on the right of the screen to schedule at a later time.